The most expensive sentence in charger procurement is "the sample was fine." It is said after a container lands with units that run hotter than the sample, hum under load when the sample was silent, or carry a transformer from a different winder than the one the test house evaluated. None of that is fraud, necessarily. It is what happens when custom power adapter sample approval before mass production is treated as a look-and-feel check instead of a controlled hand-off with a paper trail. This article walks through the stages between the spec you send and the golden sample you sign, what to measure at each one, and which documents turn "fine" into something you can hold a production lot against.
Stage 0: the spec you send determines the sample you get
A power-supply plant quotes and builds against a small number of inputs. Lexiang Power's own contact block lists them plainly: output voltage and current, plug markets, target quantity, and any certification you need — from which its team returns a specification and a quote. That list is a good minimum, and it is worth seeing why each item matters before the first sample is built.
- Output voltage and current fix the topology and the transformer. A 12 V 2 A adapter and a 12 V 3 A adapter are different boards, not a trim-pot adjustment.
- Plug markets fix the enclosure variant and, more importantly, which safety file the product has to sit in. A unit for North America is evaluated against UL 62368-1 or UL 1310; the same board going to the EU needs an EN 62368-1 report; the UK needs the BS 1363 plug and the corresponding conformity route. Each is a separate certificate the buyer should demand for the exact model number, held by a named entity, with its own expiry.
- Target quantity decides whether the supplier builds your sample on existing tooling or proposes something new, which is the same fork described in the earlier piece on charger housing tooling and when a mould is needed.
- Certification required decides which components go on the board. This is the point most buyers miss and it is the crux of the whole sign-off: a safety file lists critical components by manufacturer and part number, and the sample you approve must be built from that list.
Add to the supplier's minimum list the things that only you know: the DC connector and cable length, the load profile (continuous or peak), the ambient temperature of the end product, the efficiency regime you must meet (DoE Level VI for a North American external supply, ErP for the EU), the label content, and the packaging. The template in how to write a product spec sheet for a Chinese factory covers the general structure; for an adapter, the items above are the ones that decide whether the sample is representative.
The three samples, and why they are not the same object
Buyers talk about "the sample" as if there is one. There are three, and confusing them is where programmes go wrong.
| Sample stage | What it is built from | What it proves | What it does not prove |
|---|---|---|---|
| Engineering sample (ES / EVT) | Bench-assembled board in an existing or 3D-printed housing; components from stock, not necessarily the ones on the safety file | Electrical function: output regulation, ripple, protections (OVP, OCP, SCP, OTP) trigger at the intended points | Thermal behaviour in the final enclosure; manufacturability; compliance |
| Pre-production sample (PPS / DVT) | Production board, production housing, critical components per the safety-file list, built by hand or on a pilot run | Thermal margin, hipot pass, no-load and efficiency numbers, label and artwork, fit of plug bodies and cable | Line-to-line consistency; what 5,000 units look like |
| Golden sample (PVT / sign-off) | Units pulled from a pilot run on the production line, with production processes — wave soldering, ultrasonic welding, laser marking, burn-in — applied | The reference the mass-production lot is judged against | Nothing further — this is the standard, and it is only useful if it is sealed and signed |
Two details separate people who have run this process from people who have read about it.
First, ask which stage the sample you are holding belongs to. A supplier under time pressure will send an engineering sample as "the sample" because it exists. It will look right. It may be built from whatever optocoupler and Y-capacitor were on the bench that day. If you approve it, you have approved a board that will not be built that way in production.
Second, the golden sample must come off the line, not the bench. A plant that lists lead-free wave soldering, ultrasonic welding and automated burn-in as its processes — Lexiang's page does — should be asked to build the sign-off units through exactly those processes, with the burn-in log attached. A hand-soldered golden sample tells you what an engineer can make, not what the line will make.
What to measure before you sign, and what evidence to demand
A sample is not approved by looking at it. Here is the test set a competent buyer or a third-party lab runs on pre-production and golden samples, with the evidence that should come with each unit. None of these figures should be numbers you take from the supplier's brochure; they are measurements on your units.
- Output regulation and ripple at no load, half load and full load, at the nominal input and at the low and high line voltages for your markets (90 V and 264 V AC covers most). Ripple and noise measured with a 20 MHz bandwidth limit, stated on the report.
- Protection trips. Over-voltage, over-current, short-circuit, over-temperature: at what point does each trigger, and does the unit recover (auto-restart) or latch? Which behaviour you want depends on the end product, and it has to be written in the spec.
- Thermal rise at full load in the final housing at your maximum ambient, for long enough to reach steady state (typically 2–4 hours). Transformer, primary switch, output rectifier, and the housing surface. Compare against the limits the safety standard sets for touchable surfaces and for the insulation class of the transformer.
- Hipot (dielectric strength) primary-to-secondary and primary-to-enclosure at the standard's test voltage. Production lines should run this on 100% of units; the sample report should show the same test.
- No-load input power and average active efficiency at the input voltage your regulation specifies. If your market requires Level VI or ErP compliance, this is a buyer requirement, and the supplier should produce a test report per model that you can check against the marking on the label.
- Plug-body and connector fit: gauge checks on the pins for the plug standard, cable pull, and connector polarity and barrel dimensions against the drawing.
- Label and marking: model number, ratings, safety marks as required in your market, efficiency mark, polarity symbol, manufacturer name — and crucially, that the model number on the label matches the model number on the certificate you were shown.
The evidence to file alongside the signed sample: the supplier's own test data for these units (a plant with in-house high/low-temperature chambers and combined testers can produce it — ask whether Lexiang or any supplier will release in-house lab data pre-order, since that is not a stated policy), the burn-in record for the sample units, the critical-component list that matches the safety file, and photographs of the board with the component markings legible.
The deviation list: the document that makes the sample enforceable
A golden sample on its own is a physical object in a drawer. What makes it contractual is the paperwork around it. Ask for — or draft yourself — a sample approval sheet with four parts:
- Identification. Model number, revision, date, serial numbers of the sealed units (usually two or three: one at the supplier, one with you, one with your inspection company).
- Measured values. The test results above, recorded for the specific sealed units, with instruments and conditions noted.
- Critical component list. Transformer (winder and part number), primary switching IC or controller, optocoupler, X and Y capacitors, fuse, bulk electrolytic capacitor (brand, voltage, temperature rating), output rectifier, and the housing resin grade. This list should match the one on the safety file. Any substitution after sign-off requires a written change notice and, for components on the safety file, the test house's agreement.
- Deviation list. Anything on the sealed sample that differs from the spec, or that the supplier has said will differ in production. Empty is acceptable; absent is not. A deviation list that says "production units will use pad printing instead of laser marking" is a legitimate note; discovering it in a container is not.
A deviation list also protects the supplier, which is why serious plants will produce one without being pushed. It fixes what "the same as the sample" means, and it gives the inspection company a document to work from at pre-shipment. Whether a signed golden sample and deviation list is standard practice at a given supplier is a question worth asking directly; the answer tells you something about how many brand customers they have run.
Timeline, cost and revisions — the questions the page does not answer
Three practical questions come up on every programme and are rarely on a supplier's public listing. Lexiang's page, for example, shows sampling lead time as "Contact via CMH", which is the honest answer for a custom spec: it depends on whether the sample uses existing tooling and existing certified boards, or needs either to be new. Ask for the number for your spec, and ask it in three parts — engineering sample, pre-production sample, golden sample — rather than one aggregate.
Sample charges follow a similar pattern across the industry: a fee for the first units, often credited back against the first production order, with a set number of revisions included before further charges apply. None of those terms is stated on the factory page. Write into the RFQ what you expect — for instance, sample fee credited against a first order above an agreed quantity, and two revisions included — and let the supplier counter. The general sequence is covered in the sample order process at a Chinese factory, and the calendar from sample to first lot in sample to mass production timeline; for an adapter, the certification step is the long pole, so start it at pre-production stage, not after golden sample.
A supplier's engineering depth shapes how many revisions you will need. A plant that describes over 40 engineering and quality staff alongside more than 200 employees, and separates the engineering front-end and certification office in Shenzhen from the Hubei plant, is telling you where your revision requests will be handled and by whom. Ask who your named engineering contact is and which entity issues the sample invoice and appears on the certificate — the factory page itself notes that the answer affects your documentation.
Sign-off process you can put in a purchase order
- Send the spec: output, connector, plug markets, quantity, certification required, efficiency regime, ambient, protections behaviour, label content.
- Receive the supplier's counter-specification and quote; confirm which safety file (model number, holder, expiry) the product will sit under.
- Engineering sample: verify function only. Do not approve.
- Pre-production sample: run the full test set above; verify the critical component list against the safety file.
- Resolve deviations; agree a revision if needed.
- Golden sample from a pilot run through production processes, with burn-in log; three sealed units; signed approval sheet with measured values, component list and deviation list.
- Attach the approval sheet to the purchase order as the acceptance standard, and to the pre-shipment inspection brief.
What to ask the supplier next
- Which stage is the sample you are sending me — engineering, pre-production, or line-built?
- Is the sample built from the critical component list on the safety file for my market, and can I see that list?
- What is the sampling lead time for my spec, split by stage, and what is the sample charge and credit policy?
- How many revisions are included before charges apply?
- Will you produce a signed sample approval sheet with measured values and a deviation list, and keep a sealed unit?
- Can in-house test data for the sample units (thermal, hipot, no-load, burn-in) be released to me before the order?
- Which entity — plant or head office — invoices the sample, and which one holds the safety file?
Lexiang Power is a reasonable example of the profile to look for: a plant with stated in-house test capability and a separate engineering and certification front-end, quoting from the four inputs in its contact block. Confirm each of the points above with them in writing, and read the factory profile alongside your spec sheet before the first sample is built.