"Please quote a meatball line" is the inquiry that produces the slowest, vaguest and most expensive reply. The supplier has no idea whether you make 200 kg a day for a restaurant group or 20 tonnes for a frozen-food distributor, whether your raw material arrives as chilled trim or frozen blocks, or whether the room is 8 metres wide with a drain in the wrong corner. So the sales engineer either sends a catalogue, or configures a line for someone else's plant and prices that. Knowing what to send a food processing machinery supplier for a quote is the difference between a usable configuration in a week and three rounds of "please clarify."

GanYun Food Machinery, a Ganzhou plant that lays out meatball, sausage, pre-cut vegetable and prepared-food lines to the buyer's floor plan, puts the request in one sentence on its factory page: send your product, target output per shift, plant layout and any certification your market needs, and the team will come back with a line configuration and a quote. That sentence is a good skeleton. This article fleshes it out into an RFQ pack a sizing engineer can actually work from — and flags the pieces a first-time buyer usually leaves out.

Why the four items are the four items

Each element of that sentence answers a question the supplier cannot guess.

  • Product decides which machines. Beef meatballs and fish balls both come off a "meatball line," but the front end (grinder versus surimi refining), the beater programme and the cooking temperature are all different.
  • Output per shift decides how big. Every station on a line has a rated throughput, and the line is sized so no station bottlenecks the target. Without a number, the supplier picks a default — often the reference configuration it has drawings for — and you find out later it is double or half what you needed.
  • Plant layout decides the shape. A line laid out to your floor plan has to fit through your doors, around your columns, and flow from raw to cooked without crossing back. It also decides conveyor lengths, which are real money.
  • Certification your market needs decides what gets built into the machines from the start — control-panel standards, guarding, materials, documentation — rather than retrofitted. GanYun states that it does not currently hold EU or U.S. market-entry product certificates on file with CMH, and tells buyers to raise the point at inquiry stage. That is the right time: a conformity requirement discovered after the machines are built is a rebuild.

The RFQ pack, item by item

Here is the pack laid out as a table. The third column is what tends to go wrong when the item is missing — which is also your argument for spending an afternoon assembling it.

Item What to include What happens if you leave it out
Product definition Product name, raw material and its state on arrival (chilled, frozen block, block size), fat/lean or species, final product form (ball diameter, sausage calibre, dice size) Wrong front-end machine; forming heads or cutting sets sized for another product
Output target Kilograms or pieces per shift, shift length, shifts per day, days per week, and any seasonal peak Line sized to the supplier's reference, not yours
Batch versus continuous Whether you run batches (recipe-driven, e.g. beating and cooking) and the batch size you want Beater and cooker capacities mismatched to each other
Process boundary Where product enters the supplier's scope and where it leaves (e.g. "frozen blocks on pallet" to "cooked product in crates") Missing stations at either end; freezing or packaging assumed one way or the other
Floor plan Dimensioned plan with column grid, door openings, ceiling height, drain positions, existing equipment to keep, product-flow direction, wall finishes Layout redrawn two or three times; conveyors too long or impossible
Utilities Electrical supply (voltage, phase, frequency), steam or gas availability and pressure, water supply and temperature, compressed air, drainage capacity Machines built for the wrong supply; cooking method chosen by default
Hygiene and materials Washdown regime, chemical sanitisers used, stainless grade expectations for product-contact parts, allergen or segregation needs Standard build offered; upgrades quoted later at higher cost
Market and conformity Destination country, applicable machinery and electrical rules, who will hold any certificate, whether a third-party evaluation is planned Conformity treated as afterthought; documentation gaps at import
Automation level Manual, semi-automatic or automated transfer between stations; whether a master control panel is wanted Islands of machines with no interconnection quoted
Packaging format Bulk, tray, vacuum, modified-atmosphere; pack weights and tray sizes Packaging station omitted or wrong tooling
Commercial frame Target Incoterm and port, payment structure, required delivery date, contract entity preference Quote on default terms that then need renegotiating
Sample plan Whether you will send product for trials, and whether you want a sample run before ordering Trial opportunity missed; GanYun states sampling of 7–15 days, but only if you ask

Output per shift: the number everyone gets wrong

Suppliers ask for output per shift for a reason, and buyers routinely give a number that is not what the sizing engineer needs. Four errors show up constantly.

Per hour versus per shift versus per day. A 2,000 kg/h grinder and a 2,000 kg/shift target are a factor of eight apart. State the shift length and the number of shifts, then give the per-shift figure. If your plant will grow, give today's number and a two-year number separately — sizing to the two-year figure now can be cheaper than a second line later, but it is your call, not the supplier's.

Input weight versus output weight. A meatball line loses water in cooking; a sausage line gains water and binders in mixing; a vegetable line loses trim and peel. State whether your target is raw material in or finished product out. For pre-cut vegetables, yield losses of 20–40% between whole produce and packed product are ordinary, so a line quoted on output weight is markedly larger than one quoted on input weight.

Batch-rated stations. Beaters, mixers, tumblers and cooking tanks work in batches. A beater rated in kilograms per batch, with a cycle time, gives a kg/h figure only after you multiply out loading, beating, discharge and cleaning time. This is why GanYun describes its meatball reference configurations as rated around two tonnes per batch rather than per hour — a batch rating is honest about how these stations run. Your job is to tell the supplier how many batches per shift you intend to run, so the continuous stations (grinding, forming) can be matched to the batch stations.

Peak versus average. If you have a seasonal or weekly peak, state it. A line sized to average throughput will run overtime for the peak; a line sized to peak will run under capacity most of the year. Engineers usually apply a 20–25% margin above the stated target to allow for cleaning, changeovers and stoppages; tell the supplier whether your figure already includes that margin or is the net product you must ship.

An insider detail: product temperature at the grinder infeed is a sizing input, not a footnote. Frozen block at −18 °C into a grinder requires a different machine and a lower rated throughput than chilled trim at 2 °C. If your raw material sometimes arrives frozen and sometimes chilled, say so — the plant may recommend a flaker or a frozen-capable grinder at the front end rather than relying on tempering time you may not have.

The floor plan: what "to the buyer's floor plan" requires from you

A plant that lays out lines to your drawing is offering design work. It can only do that with a drawing that contains what a layout engineer needs.

Send a dimensioned plan — not a photograph of a sketch — with:

  1. Room envelope and column grid, including any columns inside the room, because conveyors cannot pass through them.
  2. Door and opening sizes, including the route from the loading dock to the room. The biggest machine has to fit through the smallest opening on that route, and a cooking tank frequently does not.
  3. Ceiling height and any ducting, pipework or lighting hanging below it, since hoppers and elevating conveyors are the tallest items.
  4. Floor drains and floor slope, because washdown equipment should sit where water goes.
  5. Utility entry points: the electrical distribution board, steam or gas main, water and compressed-air drops.
  6. Product-flow direction and hygiene zones: where raw material enters, where cooked product leaves, and any wall or line between low-risk and high-risk areas. A line that flows raw-to-cooked without crossing is the whole point of laying out to the plan.
  7. Existing equipment to be kept, with dimensions and interface heights, so new conveyors meet old ones.

Ask the supplier what drawing format it prefers — DWG, PDF or both — and whether the layout proposal is free at inquiry stage or chargeable. Neither answer is in GanYun's fact basis, so treat them as questions, and get the answer before you spend engineering hours preparing the file. If you have no CAD, a scaled hand drawing with every dimension written on it is acceptable to most plants; an unscaled sketch with no numbers is not.

Recipe and formulation: how much do you have to disclose?

Buyers are understandably reluctant to send a recipe to a supplier. The honest answer is that sizing some stations depends on formulation, and others does not.

  • Grinding, slicing, cutting and forming can be sized from product type, raw material state and output. Formulation is not needed.
  • Beating, mixing and tumbling depend on batch size and cycle time, which in turn depend on how much water, starch, binder or ice the recipe carries and the texture you want. A supplier may ask for the ratio of meat to added ingredients, not the ingredient list.
  • Cooking depends on ball size, target core temperature and whether product goes in raw or pre-set; cooking tank sizing follows from dwell time, which follows from those.

Whether a given plant requires the recipe or formulation to size beaters and cookers is not stated for GanYun — ask what the minimum information is. Most sizing questions can be answered with a product data sheet that gives proportions and target texture without naming ingredients, and a non-disclosure agreement covering anything more detailed. The general approach to writing a product spec sheet for a Chinese factory applies: state what the machine has to do to the product, not how you make the product.

Utilities and conformity: the two items that get retrofitted

Two items in the pack determine what is built into the machine at the start, and both are expensive to change after.

Electrical supply. State voltage, phase and frequency explicitly — for a U.S. plant, typically 480 V three-phase 60 Hz for large motors and 208 or 240 V for smaller units. Chinese plants build to 380 V 50 Hz by default. A 60 Hz build changes motor speeds by 20%, which for a grinder or a cutter can change rated throughput and blade speed, and may mean different gearboxes or inverters. What options GanYun offers and whether a surcharge applies are not in the fact basis; put your supply on the first page of the RFQ and ask how the plant handles it.

Conformity and documentation. If your market requires a technical file, a declaration of conformity, an electrical-panel evaluation or food-contact material declarations, say so in the RFQ and say who will hold the documents. This is exactly the instruction on the GanYun page — raise it at inquiry stage — and it matters because guarding, panel component selection, labelling and manuals in the right language are cheap to include at build and costly afterwards. Whatever documents you are later shown, check the issuing body, the holder name and the validity date on the document itself. The broader list of documents to ask a Chinese supplier for before a first order is the baseline; for machinery, add the conformity set for your destination.

An RFQ assembly checklist

Work through it once, save it, and reuse it for every food machinery inquiry.

  • [ ] Product data sheet: product, raw-material state and temperature at infeed, final form and dimensions
  • [ ] Output target per shift with shift length, shifts per day, days per week, seasonal peak, and whether the figure is input or output weight
  • [ ] Batch sizes and batches per shift for beating, mixing and cooking
  • [ ] Process boundary: first and last step in the supplier's scope
  • [ ] Dimensioned floor plan with the seven items above
  • [ ] Utility schedule: electrical supply, steam/gas, water, air, drainage
  • [ ] Hygiene regime and materials expectations
  • [ ] Destination market, applicable rules, certificate holder
  • [ ] Automation and control expectations, including master panel
  • [ ] Packaging format
  • [ ] Incoterm, port, payment structure, required date, preferred contract entity
  • [ ] Sample request: product you will send, what you want demonstrated

Suppliers respond to this pack differently, and the response is itself information. A plant that comes back with a layout proposal, a station list with rated capacities and a list of clarifying questions is engineering your line. A plant that comes back with a catalogue price list is selling machines. Both can be fine — the two paths are compared in buying one machine versus quoting a turnkey line — but you should know which one you are getting.

What to ask the supplier next

Once the pack is sent, these questions get you from configuration to a comparable quote.

  1. What drawing format do you prefer for the floor plan, and is the layout proposal free at inquiry stage?
  2. What is the minimum product information you need to size the beater and the cooker — proportions and texture target, or the full recipe?
  3. What electrical supply will the machines be built to, and does a 60 Hz build change any rated throughput?
  4. Which stations in your proposed configuration are batch-rated, at what batch size and cycle time, and how do they match the continuous stations at my output target?
  5. Which entity will sign the contract and hold any conformity documents for my market, and what does installation and commissioning support look like — the shape of after-sales for imported machinery should be on the table from the first reply?

GanYun Food Machinery is a fair place to send this pack as written: the plant's own inquiry instruction asks for product, output per shift, plant layout and market certification needs, offers sampling in 7–15 days, and lays out lines to the buyer's drawing. Send the full pack through the factory profile rather than the one-line version, and compare what comes back against the twelve items above — the gaps in the reply are the gaps in your eventual quote.